130 - Første bilder
Her er de første bildene av NB 130 ved verftet i Polen. Byggingen har nettopp startet, og skroget er ventet til Flekkefjord i løpet av høsten 2013.
Here are the first pictures of Yard no. 130 at the construction site in Poland. The construction has just begun, and the hull is expected to Flekkefjord during fall 2013.
|
|
125 - First pictures
Here are the first pictures of Yard no. 125 from the construction site in Poland. The ship will be delivered medio May 2013 to Atlantic Offshore.
|
126 - C-Viking has now departed Simek
Yard no. 126, C-Viking departed Simek this morning, 18/07/2012. The ship is now headed for West-Africa where she will be supplying Oil Platforms with food and other goods.
|
126 - C-Viking has been delivered!
Yard no. 126 was delivered to Duh Boats 2 Partnership C.V. ( Edison Chouest Offshore) at Simek 12/07/2012. The ship will depart Simek in the beginning of week 29.
|
126 - Fi-Fi testing at sea
The crew onboard yard no. 126 continues to test the ship. The Fi-Fi (Fire Fighting) was tested today, 8/7/12. The ship will be delivered on 12th July 2012 to Duh Boats 2 Partnership C.V (Edison Chouest Offshore).
|
126 - First part of seatrail completed
Yard no. 126 started it's seatrail outside Simek today, 7/7/2012. Part one is completed, and tonight, they will test the engines by running them at 100 % in 24 hours. The ship will be delivered on Thursday 12/7/12.
|
|
126 - Project update week 27-12
The work on Yard no. 126 at Simek continues. The ship is starting it's seatrails on Saturday 7/7/12, and will be delivered next week on Thursday 12/7/12
|
126 - Project update week 25-12
Yard no. 126 is at the end of the construction. In three weeks, all work will be done. The ship will be delivered 12th of July 2012 to Duh Boats 2 Partnership C.V.
Seatrails 7th July 2012.
|
|
We have recieved new pictures from the yard in Poland. The dry bulk tanks are now completed and ready to be assembled to the hull.
|
|
It's just one month left until delivery! On Tuesday 12th June 2012, the Cargo crane was being installed, and chairs/tables was placed in the Mess Room.
|
Pilot boats are being painted
Last week, we sandblasted and painted the first of two pilot boats. Today, the first boat was sealaunched, and the second boat was taken onshore, also to be sandblasted and painted.
|
Ny kontrakt! Bygg nr.127
Simek A/S har signert kontrakt med rederiet Simon Møkster Shipping AS i Stavanger. Det blir verftets nybygg nr. 127.
|
126 - The work continues
The exterior and interior work on NB 126 continues. Today, the MOB/Rescue boat arrived, and will be installed later.
|
|
126 - Interior work has started
The interior work on yard no. 126 has started at Simek 23/05/2012. The ship will be delivered on 12th of July 2012 to Duh Boats 2 Partnership C.V
|
|
|